How long does it take to design a custom home?

Published 5 min read

Covered alfresco deck with ceiling fans and an outdoor kitchen opening to the kitchen at Walker House, Coorparoo
On this page

The design stage of a custom home typically takes about six to eight weeks, from the first brief to a full design with elevations that's ready to quote. Working with our architects and designers, the first floor plans take about two weeks, and each round of revisions takes about one to two weeks. That means the number of changes you make is what moves the timeline most.

This guide walks through what happens at each step, what tends to slow the design down, and what comes next.

How long does each step of the design take?

The times below are typical for a custom home and are approximate. Every home is different, and the number of revisions is the biggest variable.

StepWhat happensTypical time
Brief and siteYour goals, budget and how you want to live, plus what the block allowsBefore drawing starts
First floor plansThe first layout of the home on your blockAbout 2 weeks
RevisionsChanges to the layout, room sizes and how the home sits on the siteAbout 1 to 2 weeks per round
Full design with elevationsThe finished floor plans and elevations, ready for an energy assessment and a quoteAbout 6 to 8 weeks in total, on average

What happens before the first drawings?

The design starts with the brief. We begin by understanding your goals, your budget and your site conditions, then work with our architects and designers to turn them into a concept.

A good brief covers how you want to live in the home: the number of bedrooms, how you use the kitchen and living areas, whether you work from home, and how the home should connect to the yard, alfresco or pool. It also covers your budget, because a design drawn without one often has to be redrawn.

The block matters just as much. A contour survey shows the levels across the site, and a soil test shows what the ground is like, which shapes the footings and slab. Our guide to what a soil test tells your builder explains why it's worth getting early. On a sloping, narrow or corner block, the site often decides more of the layout than the brief does.

How long do the first floor plans take?

Working with our architects and designers, the first floor plans typically take about two weeks. They show the layout of the home on your block: where each room sits, how big it is, and how the home relates to the street, the sun and the yard.

If you already have an architect or designer, or plans of your own, we can work from those instead.

How many revisions should you expect?

Each round of revisions typically takes about one to two weeks. Revisions are where most of the time in the design stage goes, and where it varies most from one home to the next.

That's not a reason to rush them. Revisions are where a home starts to fit the way you live. The aim is to make the bigger decisions early, when they're quick to change on paper, and keep later rounds for refinement.

When is the design ready to quote?

The design is ready to quote once the floor plans and elevations are complete. On average, that's about six to eight weeks from the start of design.

Before we quote, the design goes through an energy assessment. Most new homes in Queensland have to meet the 7 star energy rating, and the report shows what the home needs to get there, such as the type of glazing, insulation and ceiling fans. Quoting after the report means those items are in the price from the start. The design also needs to meet the Livable Housing Design Standard, which covers things like a step-free entry and wider doors and corridors.

Our guide to what's included in a custom home building quote covers what the quote itself should set out.

What can slow the design stage down?

Most delays come from a few common causes:

  • More rounds of revisions. Each round adds about one to two weeks.
  • Big changes after the elevations are done. Moving rooms, changing the roof or enlarging windows late can mean redrawing and reassessing. Larger windows in particular can bring the energy rating down, which may mean other changes to compensate.
  • A brief or budget that isn't settled. If priorities change partway through, the design often changes with them.
  • Surprises on the site. An easement, an overlay or a steeper fall than expected can change where the home can sit.

How can you keep the design on track?

  • Bring a clear brief. List your must-haves and your nice-to-haves, and collect a few images of homes and spaces you like.
  • Be upfront about your budget. It's much easier to design to a budget than to cut a design back later.
  • Get the site information early. The survey, soil test and any overlays on the block all shape the layout.
  • Make the big decisions first. Settle the layout, the number of levels and how the home sits on the block before getting into finer details.
  • Think about windows before the elevations. Window sizes affect the look, the light and the energy rating, so they're best settled before the energy assessment.

What happens after the design is finished?

Once the design is complete and the energy assessment is done, we prepare the quote. After the contract is signed, the design moves into detailed drawings, engineering and approvals. From design to building approval and being ready for construction typically takes about five to six months. Your building certifier checks the plans before they're approved.

For the build itself, see our guide to how long it takes to build a house in Brisbane.

Frequently asked questions

Do I need plans before I talk to a builder? No. You can start the conversation well before you have plans. Involving a builder early helps keep the design in line with your budget and what the block allows.

Can I use my own architect or designer? Yes. If you already have an architect, a designer or plans of your own, we can work from those. If you don't, we work with the architects and designers we know to develop the design.

Does a sloping block take longer to design? It often needs more thought, because the design has to work with the levels across the site, and the retaining, footings and access all affect the layout. Getting the survey and soil test early helps.

Is the design stage the same as getting approval? No. The design stage ends with floor plans and elevations ready to quote. Approvals come after, once the detailed drawings and engineering are done, and typically take about five to six months to be ready for construction.

Check your block before the design starts

The design goes faster when the brief, the budget and the site are clear from the start. A free feasibility check shows what your block allows before any drawings begin. Flascon Construction Group is a custom home builder in Greenslopes, Brisbane, and we can talk you through how our custom home builds run from the first brief to handover.