What a Soil Test Tells Your Builder Before You Build in Brisbane

Published 6 min read

Orwell House, Coorparoo, a completed custom home by Flascon Construction Group before landscaping, with the driveway poured and stormwater drainage in place
On this page

When planning a new custom home in Brisbane, the soil test is one of the first reports your builder will ask for and one of the last you are likely to read. It is a short document, it is one of the cheapest items in the whole project, and it decides the design of everything the house stands on. The classification on the front page tells the engineer how much the ground is expected to move, and that single letter drives the slab, the footings, the excavation and, on a lot of Brisbane blocks, a meaningful share of the site cost. This guide explains what the test involves, what the classification means, and why Brisbane's ground makes it worth doing early.

Understanding the Soil Test

A geotechnical engineer or technician visits the block and bores two or more holes across the building footprint, typically to a depth of a few metres. The soil is logged layer by layer (topsoil, fill, clay, sand, weathered rock) and samples go to a laboratory to measure how reactive the clay is to changes in moisture. The report records what was found at each depth, where the water table sat if it was encountered, whether there is fill or anything unusual, and then assigns the site a classification. The work on site takes a morning; the laboratory results and report follow a couple of weeks later.

The classification comes from AS 2870, the Australian Standard for residential slabs and footings. First published in the 1980s and now in its 2011 edition, it exists because Australia's clay soils swell when wet and shrink when dry, and a house built without allowing for that movement will crack. The standard gives engineers a shared language for how much movement to design for.

What the Site Classification Means

The letters on the report grade the expected ground movement, and each one points to a different kind of foundation:

ClassWhat it meansWhat it usually means for the slab
ASand or rock, little or no ground movementThe simplest slab and footings
SSlightly reactive clay, slight movementA standard slab with modest stiffening
MModerately reactive clay, moderate movementA stiffened slab with deeper edge beams
H1 and H2Highly reactive clay, high to very high movementA heavily stiffened or waffle slab, or piers to stable ground
EExtremely reactive clayAn engineered solution, often piers or a suspended floor
PProblem site: fill, soft soil, mine subsidence or unusual conditionsDesigned case by case, often piers through the fill

The engineer takes this classification, the contour survey and the architectural drawings and designs the footings and slab to suit. A class M site and a class H2 site can carry the same house, but the concrete, the steel and the excavation under it will be different, and so will the cost. Our guide to what a new home builder does before the slab is poured shows where the soil test sits in that sequence.

Why Brisbane Ground Is Worth Testing

Brisbane sits on a mix of ground that changes from one street to the next, and three conditions come up often enough to be worth knowing about:

  • Reactive clay. Common across many inner and southern suburbs, it swells and shrinks with the seasons, which is exactly what the M, H and E classes describe. It is the reason so many Brisbane homes sit on stiffened or waffle slabs.
  • Rock close to the surface. Some ridgelines have rock within reach of the excavator. It is stable to build on but costly to dig, and until the ground is opened it is often carried in the contract as a provisional sum.
  • Fill on older blocks. A block that has carried a house, a filled gully or an old pool may be sitting on uncontrolled fill, which pushes it toward class P. Knockdown rebuild sites are where this turns up most, and our guide to the knockdown rebuild process in Brisbane explains why the test is usually done after demolition rather than before.

None of this is a reason not to build. It is a reason to know before the price is set. A soil test turns "we will allow for the footings" into a designed and quoted slab.

When to Get the Test Done

The short answer is before the builder prices the job, wherever the programme allows. A soil test and a contour survey together let the engineer size the footings and let the builder quote the site work rather than carry an allowance for it. That is the difference between a price that holds and one that moves at the earthworks stage, which our guide to building contracts in Queensland covers in more detail.

On a knockdown rebuild there is a wrinkle: the existing house covers the ground you most need to test. In that case the test is done once the site is clear, or a preliminary test is done in the yard for pricing and repeated on the building footprint after demolition.

What the Report Changes on Site

The classification decides the slab type, the depth of the edge beams, whether piers are needed and how deep they go, and how the site needs to be drained so water does not sit against the footings. On a sloping block it also feeds the retaining wall design, because a wall holding reactive clay is designed differently from one holding sand. Our guide to sloping block home designs covers how the slope and the soil work together, and our difficult site guide helps you work out which constraints apply to your block.

The report shapes life after handover, too. On a reactive clay site, keeping garden beds and irrigation away from the slab edge and maintaining even moisture around the house is part of how the slab performs over its life. That advice comes from the geotechnical report, not from anyone's preference.

How to Read the Report

You do not need to read the bore logs. Look for three things:

  • The site classification, usually on the first page.
  • Any mention of fill or a problem condition, which is the trigger for a class P and for piers.
  • The recommended footing system, which tells you whether the engineer expects a standard stiffened raft or something more involved.

If the report says class M with a standard stiffened raft, the site is ordinary. If it says class H2 or P and recommends piers to a stated depth, expect the engineering and the site cost to reflect that, and expect the quote to have priced it rather than allowed for it.

Frequently Asked Questions

Do I need a soil test to build a house in Queensland? In practice, yes. The structural engineer cannot design the footings and slab without a site classification, and the building certifier will expect the engineering to reference it. A price prepared without one is carrying an allowance for the ground rather than a quote.

What does site classification M mean? Class M under AS 2870 is a moderately reactive clay site, where the ground is expected to move moderately with changes in moisture. It usually calls for a stiffened slab with deeper edge beams than a class A or S site, and it is one of the most common classifications on Brisbane blocks.

How much does a soil test cost? It varies with the size of the site, the number of bores and the depth required, so ask for a quote for your block. Relative to the slab and footings it is designing, it is a small figure that removes a large unknown from the price.

Should the soil test happen before or after demolition on a knockdown rebuild? After, where the programme allows, because the old slab hides the ground you need to test and older sites often contain fill. If pricing needs a result earlier, a preliminary test can be done in the yard and repeated on the building footprint once the site is clear.

The ground under your home is the one part of the project you cannot change, which is why the soil test comes so early and matters so much. With over 30 years of combined experience bringing custom homes to life across Brisbane, the team at Flascon Construction Group, custom home builders in Brisbane, is here to guide you. Contact us today.