Provisional Sums vs Prime Cost Items in Queensland

Published 7 min read

Galley view of a kitchen with an induction cooktop, stone splashback and butler's pantry at Walker House, Coorparoo
On this page

When you read through a building contract in Queensland, two terms come up again and again: prime cost items and provisional sums. Both are allowances, which means they're the parts of the price that can still move after you sign.

A prime cost item is an allowance for something you haven't chosen yet, such as tiles, tapware or an oven. A provisional sum is an estimate for work that can't be priced exactly until it's assessed or carried out, such as rock removal or earthworks. In both cases the allowance is compared with the actual cost once it's known, and the contract price goes up or down to match. This guide explains how each one works and what to check before you sign.

What is a prime cost item?

A prime cost item, often shortened to PC item, is an allowance for a fixture, fitting or material that hasn't been selected when the contract is signed, or whose price isn't known yet. Queensland's building contract law describes it as an item for which the builder makes a reasonable allowance to cover its supply and delivery.

Common examples include:

  • Floor and wall tiles
  • Tapware and bathroom fittings
  • Built-in kitchen appliances

The allowance covers the item itself, supplied and delivered to site. The final cost depends on what you choose. The QBCC's own guidance gives a simple example: if the contract allows $1,000 for an oven and cooktop and you choose a pair that costs $1,500, you pay the increase. Choose something under the allowance and the difference comes off the price.

That's why prime cost items deserve a close look on a custom home. If you already know you want a particular stone, tile range or appliance brand, check that the allowance reflects it.

At Flascon, we set prime cost allowances during the preliminary stage, once we understand the style of home and the level of finish you're after. If you've told us you'd like timber floors, a particular look for your tiles or a certain tapware range, the allowance in the quote is matched to that and to your budget. After the contract is signed, you choose the exact products through the colour selection process, and you can upgrade or downgrade from there.

What is a provisional sum?

A provisional sum, or PS, is an estimate of the cost of a particular part of the work. Under Queensland law, a builder can only use one for work where, after making all reasonable enquiries, they can't state a definite amount when the contract is signed. The estimate includes the materials that work needs, not just the labour.

The QBCC lists rock removal, asbestos removal and earthworks as common examples. These are all things where the true cost depends on what's found once work starts. On a Brisbane block that might be rock sitting closer to the surface than expected, old fill on a knockdown rebuild site, or extra excavation on a sloping block.

As the QBCC puts it, a builder can't be certain what earthworks will cost without knowing what's under the ground. Once the work is done, the actual cost replaces the estimate. If it costs more, the difference is added to the price. If it costs less, you receive a credit.

We aim to keep as much of each contract as possible at a fixed price, so provisional sums are kept for the parts of the work that can't be confirmed yet, such as when the engineering isn't complete or design details are still being finalised.

Prime cost vs provisional sum: the key differences

The simplest way to tell them apart: a prime cost item depends on what you choose, while a provisional sum depends on what's found on site.

 Prime cost itemProvisional sum
What it coversA fixture, fitting or material that hasn't been selected, or whose price isn't known yetWork that can't be priced exactly until it's assessed or carried out
Common examplesTiles, tapware, ovens, cooktops, dishwashersRock removal, asbestos removal, earthworks
What the allowance pays forSupply and delivery of the itemThe work itself, including the materials it needs
What moves the final costThe selections you makeWhat's found on site
If the actual cost is higherYou pay the difference, plus any margin your contract allows on the increaseYou pay the difference, plus any margin your contract allows on the increase
If the actual cost is lowerYou receive a credit for the differenceYou receive a credit for the difference
How to reduce it before you signFinalise your selections so they can be pricedGet the soil test, survey and site investigations done before the price is set

How are prime cost items and provisional sums adjusted?

When the item is bought or the work is finished, the actual cost is compared with the allowance in the contract:

  • If the actual cost is higher, the difference is added to the contract price.
  • If the actual cost is lower, the difference is credited back to you.

Many contracts also add the builder's margin to any amount over the allowance, at a percentage set out in the contract schedule. It's worth finding that percentage before you sign, so you know how an increase will be calculated.

Ask how the adjustment will be shown, too. Some contracts, including the QBCC's own, require the builder to provide supporting documents such as tax invoices or receipts for allowance items. The legislation itself doesn't require this, so it comes down to what your contract says.

At Flascon, any change from an allowance is set out in a variation document, so you can see the credit or the extra cost in writing whenever a selection changes.

Variations are the other way a price can change after signing. A variation is a change to the scope of the work, and in Queensland your builder must give you any variation in writing and have your written agreement before that work starts.

How to keep allowances to a minimum

Allowances can't always be avoided, but the earlier the decisions and investigations happen, the fewer you need:

  • Make your selections early. Tiles, tapware, appliances and other finishes chosen before the contract is signed can be priced as fixed amounts rather than allowances.
  • Get the site information before the price is set. A soil test and contour survey let the engineer design the footings and the builder price the site work. Our guide to what a soil test tells your builder explains why.
  • Investigate known site issues. On a sloping, rocky or difficult site, the more that's known about the ground, the less needs to be carried as a provisional sum.
  • Bring your builder in early. Involving a builder while the design is still developing helps keep costs in view as decisions are made.

Questions to ask about allowances before you sign

  • Which parts of the price are fixed, and which are allowances?
  • What does each prime cost allowance assume, and is it realistic for the finishes I want?
  • What information is each provisional sum based on?
  • Which selections could I make now so they can be fixed?
  • What margin applies if an allowance is exceeded?
  • How will allowance adjustments be documented?

Our guide to what's included in a custom home building quote covers the rest of what to check in a quote, from site works to exclusions.

Frequently asked questions

What is the difference between a provisional sum and a prime cost item? A prime cost item is an allowance for a fixture, fitting or material you haven't selected yet, such as tiles or an oven. A provisional sum is an estimate for work that can't be priced exactly until it's assessed or done, such as rock removal or earthworks. Both are adjusted to the actual cost once it's known.

Do I get money back if a provisional sum costs less than the allowance? Yes. If the actual cost is lower than the provisional sum, you receive a credit for the difference. The same applies to prime cost items when your selection costs less than the allowance.

Can a builder add a margin to prime cost items and provisional sums? Many contracts allow the builder's margin to be added to any amount over the allowance, at a percentage stated in the contract schedule. Check your contract for the percentage before you sign.

Is a provisional sum the same as a variation? Not quite. A provisional sum is in the contract from the start and is adjusted to the actual cost once the work is done. A variation is a change to the work after signing, which in Queensland must be in writing and agreed by you before the work starts. Some builders, including Flascon, also set out allowance adjustments in a written variation document, so you can see each credit or extra cost.

Planning a custom home in Brisbane?

Allowances are where a building price can still move, so knowing what's fixed and what's estimated is one of the most useful things you can understand before you sign. A free feasibility check is the simplest way to find out what your block will support. As custom home builders in Brisbane, we can talk you through what goes into a quote before you commit, drawing on Flascon's 30+ years of experience.